Commercial/Industrial- Boughey Distribution

Commercial/Industrial- Boughey Distribution

Client:  Boughey Distribution
Industry:  Commercial/Industrial
Generator Replacement

The Aim

To upgrade the generator supply to the LV4 panel at a critical site, ensuring improved reliability, safety, and operational continuity. The project involved the removal of the existing generator, installation of a new unit with enhanced enclosure and cabling, and full commissioning with minimal disruption to site operations.
Key objectives included:
• Safe decommissioning of the existing generator.
• Installation of a new generator with stainless steel enclosure.
• Integration with existing LV4 infrastructure and control systems.
• Full testing, commissioning, and validation of power continuity to office systems.

The Solution

A detailed and phased approach was implemented to ensure safety, compliance, and operational efficiency throughout the upgrade:
1. Site Preparation & Safety
• AWE operatives entered site wearing full PPE in accordance with safety protocols.
• Car parking spaces adjacent to the LV4 switch-room were cleared.
• Temporary road closure arranged to facilitate generator delivery.
2. Decommissioning & Removal
• Generator delivered and kept on the vehicle pending installation.
• LV4 generator supply shutdown arranged and phase rotation checked/documented.
• Generator terminals proved dead using certified tester; cable disconnected.
• LV4 panel made safe and existing XLPE SWA cable disconnected.
• Old generator lifted and relocated by specialist contractor.
3. Installation of New Generator
• New generator lifted into position using Hi-Ab (specialist contractor).
• Stainless steel enclosure installed and paxolin fitted to top section.
• Existing cable made off and fed into terminal box; cables lugged using certified crimper.
4. Testing & Commissioning
• Dead tests and phase rotation checks carried out prior to LV4 connection.
• Upon verification, start cables and SWA cable connected in LV4 panel.
• Generator started and full commissioning tests completed.
• Manual changeover executed to confirm office systems were powered correctly.
• Supply reverted to mains after successful validation.

The Outcome

The generator upgrade was completed safely and efficiently, delivering:
• Enhanced power reliability and system resilience for LV4 operations.
• Seamless integration with existing infrastructure and minimal downtime.
• Full compliance with safety and electrical standards.
• Improved operational confidence for site facilities and office systems.
This project demonstrates our capability to manage complex generator upgrades with precision, safety, and minimal disruption to business continuity.

"A potentially difficult LV4 generator replacement went extremely smoothly thanks to Andy Oliver and the AWE team."

Boughey Distribution
White industrial generator outdoors.
A metal box bolted to a white surface, with black cables extending out, resting on a gray floor.
Share by: